| Rental System Installation | | | | |
| Rental System Installation | Receive and set units in place, install air inlet hoods and shipped loose hardware | | | |
| Rental System Installation | Supply and install HDPE gas piping and shutoff valves for each C1000 and blind flange for expansion | | | |
| Rental System Installation | Install CGE supplied power cables and cable tray to each C1000 and mining box. Installation hardware supplied by CESC | | | |
| Rental System Installation | Install CGE supplied gas filter and regulator skid | | | |
| Rental System Installation | Supply and install control cable conduits to each C1000 | | | |
| Rental System Installation | Install CGE supplied PC for remote communications | | | |
| Rental System Installation | Modify C1000 for flatpac control scheme, program unit Unit #1 C1K control for master operation | | | |
| Rental System Installation | Commission units for 3MW standalone operation | | | |