Commitments and Contingencies |
3 Months Ended |
---|---|
Jun. 30, 2022 | |
Commitments and Contingencies | |
Commitments and Contingencies |
14. Commitments and Contingencies Purchase Commitments As of June 30, 2022, the Company had firm commitments to purchase inventories of approximately $48.8 million through Fiscal 2023. Certain inventory delivery dates and related payments are not firmly scheduled; therefore, amounts under these firm purchase commitments will be payable upon the receipt of the related inventories. Lease Commitments See Note 15 – Leases. Other Commitments The Company has agreements with certain of its distributors requiring that, if the Company renders parts obsolete in inventories the distributors own and hold in support of their obligations to serve fielded microturbines, then the Company is required to replace the affected stock at no cost to the distributors. While the Company has never incurred costs or obligations for these types of replacements, it is possible that future changes in the Company’s product technology could result and yield costs to the Company if significant amounts of inventory are held at distributors. As of June 30, 2022, no significant inventories of this nature were held at distributors. Legal Matters Capstone Turbine Corporation v. Turbine International, LLC. On February 3, 2020, Capstone Turbine Corporation filed suit against its former distributor, Turbine International, LLC (“Turbine Intl.”), in the Superior Court of California for the County of Los Angeles under the following caption: Capstone Turbine Corporation v. Turbine International, LLC; Case No. 20STCV04372 (“Capstone-Turbine Intl. Litigation”). The Company has alleged claims against Turbine Intl. for breach of contract and for injunctive relief relating to the parties’ prior distributor relationship, which terminated at the end of March of 2018, and Turbine Intl.’s failure to satisfy its payment obligations under certain financial agreements, namely an accounts receivable agreement and promissory note in favor of Capstone. As remedies for these claims, the Company is seeking compensatory, consequential, along with injunctive relief and attorney’s fees, interest, and costs. On March 18, 2020, Turbine Intl. filed its answer and cross-claims in the Capstone-Turbine Intl. Litigation. In its cross-claims, Turbine Intl. asserted claims against Capstone, and individually against Mr. James Crouse, Capstone’s Chief Revenue Officer, for breach of contract under the distributor agreement, accounts receivable agreement and promissory note, fraud, breach of the covenant of good faith and fair dealing, unjust enrichment and constructive trust, negligent misrepresentation, violation of the California unfair practices act, violation of racketeer influenced corrupt organizations act, and conspiracy to commit fraud. As remedies for these alleged claims, Turbine Intl. are seeking compensatory, consequential, and punitive damages along with attorney’s fees, interest, and costs. Capstone answered the cross-claims on May 7, 2020. On June 29, 2020, Capstone filed a motion to file a First Amended Complaint that would add, among other things, a claim for enforcement of a guaranty signed by an entity related to Turbine Intl., Hispania Petroleum, S.A., and personal claims against the principals of Turbine Intl. and Hispania. That motion was granted on August 19, 2020, and the First Amended Complaint (“FAC”) is now on file. All of the new defendants have been served and have filed answers. A trial date in the matter has been set for December 12, 2022. Discovery is ongoing. The Company has not recorded any liability as of June 30, 2022 as the matter is too early to estimate. |